Holly Springs, NC, Nov. 19, 2026 — The Holly Springs Town Council has approved a revised commercial plan for Carolina Springs Town Center, reducing planned retail space by about 25,000 square feet after the developer said the original layout made it difficult to attract a grocery store.
The amendment reduces commercial space from about 135,000 to 110,000 square feet and changes the building placement along Old Holly Springs Apex Road and Carolina Springs Boulevard. The developer’s team said the original design, which placed long commercial buildings along the road frontages, blocked views of the grocery store that would anchor the development.
A commercial consultant representing the developer told the council that two grocery operators had expressed interest in the property but could not accept the previous layout. The revised plan creates openings between buildings to make the grocery store more visible from surrounding roads.
The proposed grocery store would occupy approximately 51,000 square feet. The plan also includes about 52,500 square feet of additional commercial space and two outparcels totaling at least 7,000 square feet.
The developer is pursuing a mix of businesses, including fast-casual and sit-down restaurants, a dental studio, a veterinary clinic and salon, and coffee shops and bakeries. The hearing did not identify a grocery store by name or name any other tenants.
Staff Raises Concerns About Pedestrian Access
Although town staff recommended approval, its written analysis described the revised design as “overall less favorable than the currently approved Development Plan.”
A town planner told council members the new layout would be less pedestrian-friendly because additional drive aisles create more places where vehicles and pedestrians could conflict. The concerns were particularly focused on the Carolina Springs Boulevard frontage.
The developer’s representatives pointed to sidewalks and landscaping along the main drives, a 10-foot-wide side path along Carolina Springs Boulevard, and trails through lower-lying portions of the property. The plan also requires a road and pedestrian connection to a neighboring development as part of a later apartment phase.
Council members questioned the developer about replacing tree canopy in areas where buildings had been removed from the plan and improving bicycle and pedestrian connections to nearby neighborhoods and the Carolina Springs greenway.
The Planning Board previously recommended approval by a 7-1 vote, with one member absent. The dissenting member believed the reduction in commercial space went too far, while a council member acknowledged the developer’s response to concerns raised during the Planning Board review.
No residents signed up to speak at the council’s quasi-judicial hearing, leaving the developer’s team as the only presenters. Town staff reminded council members that an applicant who presents sufficient evidence of compliance with the applicable standards is legally entitled to approval.
Commercial Development Remains Tied to Housing Permits
The reduction in commercial space also matters because Carolina Springs operates under a 2019 development agreement that links residential building permits to the construction of nonresidential space.
The agreement allows up to 1,700 homes but limits how quickly residential construction can proceed until specified commercial development milestones are met. Up to 25 percent of the homes could receive building permits before plans for 20,000 square feet of nonresidential space were approved, a requirement the earlier commercial plan satisfied.
The next limit allows no more than 50 percent of the homes, or 850, to receive building permits until at least 20,000 square feet of nonresidential space has been completed.
Town staff reported that 670 homes had received building permits and 596 had received certificates of occupancy. That leaves about 180 additional residential permits before reaching the 850-home limit, unless the required commercial construction milestone has already been met.
The amendment does not change the development’s 1,700-home maximum or its existing 20,000-, 40,000- and 60,000-square-foot commercial milestones. When asked whether the revised plan affected the initial 20,000-square-foot construction requirement, the response at the hearing was that it did not, as the speaker understood the agreement.
At approximately 51,000 square feet, the proposed grocery store would exceed that first construction threshold on its own once completed. However, the materials presented did not establish how much nonresidential space has already been built or how quickly additional residential permits are being issued.
Under the agreement, the town can withhold residential building permits if required milestones are not met. The council also has authority to adjust those requirements if the developer documents exigent circumstances, including market conditions.
The developer’s engineer reported that a second builder working on the opposite side of the stream had completed more than 75 percent of its 837 home sites.
Commercial Space Shifts to Innovation District
The revised plan also transfers 10,000 square feet of the Town Center’s required commercial space to the development’s Innovation District, increasing that district’s minimum to 210,000 square feet.
Town staff said the transfer does not change plans already approved for the Innovation District. The adjustment will instead be recorded on an updated development plan sheet.
What’s Next
The developer expects to begin with the grocery store because it will take the longest to build. The developer plans to submit plans for the two outparcel buildings while grocery store construction is underway, although those parcels require separate approvals before the land can be disturbed.
During an October 2025 neighborhood meeting attended by two neighbors, the developer tentatively projected completing construction in 2029. The council discussion did not establish a firm construction schedule, and the grocery store’s identity has not been announced.